METHOD STATEMENT FOR CONSTRUCTION OF COPING BEAM
1. SCOPE OF WORK
This method statement outlines the construction procedure for coping beam on a skyway project, including formwork installation, reinforcement fixing, concrete pouring, and curing.
2. REFERENCES
-
Approved Construction Drawings & Structural Plans
-
DPWH Standard Specifications
-
ACI 318 – Concrete Design and Construction Standards
-
ASTM A615 – Standard Specification for Reinforcing Steel
-
ACI 301 – Concrete Work Specifications
3. RESPONSIBILITIES
Project Engineer
-
Ensures compliance with construction drawings and specifications.
Site Supervisor
-
Manages workforce, materials, and equipment.
QA/QC Engineer
-
Ensures quality of materials and workmanship.
Safety Officer
-
Implements safety protocols and ensures worker compliance with PPE.
4. MATERIALS & EQUIPMENT
4.1 Materials
-
Ready-Mix Concrete (as per design mix)
-
Reinforcement Bars (Grade 40/60, as per approved bar bending schedule)
-
Formwork Materials (plywood, steel, or timber)
-
Curing Compound / Wet Hessian Cloth
4.2 Equipment
-
Concrete Mixer / Transit Mixer
-
Concrete Vibrator
-
Crane / Lifting Equipment
-
Scaffolding & Ladders
-
Surveying Tools (Total Station, Spirit Level, Theodolite)
-
Cutting & Bending Tools
5. METHODOLOGY
5.1 Pre-Construction Activities
-
Survey & Layout
-
Verify coping beam dimensions and alignment using total station.
-
Mark reference points for reinforcement and formwork installation.
-
-
Material Inspection
-
Check reinforcement bars for correct diameter, length, and bending.
-
Ensure formwork materials are free from defects.
-
Verify concrete mix design approval.
-
5.2 Formwork Installation
-
Formwork Positioning
-
Install formwork firmly and securely along the edge of the skyway structure.
-
Use steel supports and bracing to prevent movement during concrete pouring.
-
-
Alignment & Level Check
-
Use spirit level or laser level to maintain correct elevation and straightness.
-
Apply release agent for smooth stripping after curing.
-
5.3 Reinforcement Installation
-
Placing of Rebars
-
Install reinforcement bars as per the bar bending schedule (BBS).
-
Ensure proper lap splicing and anchorage lengths as per design.
-
Maintain correct concrete cover using spacers and chairs.
-
-
Tying & Securing
-
Use binding wire to secure rebars in position.
-
Inspect and approve reinforcement before proceeding with concreting.
-
5.4 Concrete Pouring
-
Pre-Pour Checklist
-
Ensure formwork and reinforcement are properly secured.
-
Check slump test results (workability should match approved mix).
-
Ensure weather conditions are suitable for concreting.
-
-
Concrete Placement
-
Use crane bucket / concrete pump to place concrete uniformly.
-
Pour concrete in layers to avoid segregation.
-
Use mechanical vibrators to remove air voids.
-
-
Quality Control During Pouring
-
Perform slump test and compressive strength test (cube/cylinder samples).
-
Maintain proper curing temperature and avoid premature drying.
-
5.5 Formwork Removal & Curing
-
Formwork Removal
-
Remove side formworks after 24–48 hours (or as per strength requirement).
-
Strip bottom supports after 7–14 days, depending on curing conditions.
-
-
Curing Process
-
Apply curing compound or cover with wet hessian cloth for at least 7 days.
-
Keep surface moist to prevent cracking.
-
-
Surface Finishing
-
Inspect concrete for honeycombs or voids.
-
Conduct repair work using Pressure Injection Epoxy (PIE) if necessary.
-
6. SAFETY REQUIREMENTS
-
Workers must wear PPE (helmets, gloves, safety boots, harness for heights).
-
Ensure proper scaffolding & edge protection during work.
-
Use tag lines & safety ropes when lifting materials.
-
Prohibit unauthorized access to the work area.
7. INSPECTION & TESTING
-
Pre-Pour Inspection – Ensure proper formwork and rebar placement.
-
Concrete Strength Test – Cube or cylinder tests at 7 & 28 days.
-
Final Inspection – Check dimensions, alignment, and surface finish.
8. APPROVALS
This method statement shall be reviewed and approved by:
Prepared by:
Project Engineer
[Name]
Reviewed by:
QA/QC Engineer
[Name]
Approved by:
Project Manager
[Name]