METHOD STATEMENT FOR COLUMN PIER CONSTRUCTION

 

1. SCOPE OF WORK

This method statement outlines the procedures for the construction of a column pier for a skyway project, including excavation, reinforcement, formwork, concrete pouring, and curing.

2. REFERENCES

  • Approved Construction Drawings

  • DPWH Standard Specifications

  • ASTM & ACI Codes for Concrete Work

  • Safety and Quality Control Guidelines

3. RESPONSIBILITIES

  • Project Engineer: Supervises execution and ensures compliance with specifications.

  • Site Supervisor: Coordinates workers and material deliveries.

  • QA/QC Engineer: Monitors quality control for concrete, rebar, and formworks.

  • Safety Officer: Ensures compliance with site safety protocols.

4. MATERIALS & EQUIPMENT

  • Materials:

    • Ready-mix concrete (as per design mix)

    • Reinforcing bars (Grade 40/60)

    • Formwork materials (plywood, steel, or timber)

    • Curing compounds

  • Equipment:

    • Crane

    • Concrete pump

    • Vibrator

    • Welding machine

    • Scaffolding and ladders

5. METHODOLOGY

5.1 Survey & Layout
  • Verify column pier locations as per the approved drawings.

  • Establish reference points and levels using a total station or leveling instrument.

5.2 Excavation & Pile Cap Preparation
  • Excavate as per the structural design depth.

  • Install dewatering systems if needed.

  • Compact the base and install lean concrete.

  • Form and pour the pile cap as per structural drawings.

5.3 Reinforcement Works
  • Cut, bend, and install rebar according to approved bar bending schedule.

  • Use spacers and chairs to maintain proper cover.

  • Secure all reinforcements with binding wire.

5.4 Formwork Installation
  • Install steel or plywood formworks ensuring proper alignment and bracing.

  • Apply release agent for easy stripping.

  • Inspect formworks before pouring concrete.

5.5 Concrete Pouring
  • Use ready-mix concrete with the specified design mix.

  • Pour in layers of 1.5m max and use vibrators to remove air voids.

  • Conduct slump test and sample cylinders for compressive strength tests.

  • Allow concrete to set as per curing time specified.

5.6 Stripping of Formwork
  • Remove formworks after achieving sufficient strength (as per structural specifications).

  • Inspect for defects and conduct necessary repairs if needed.

5.7 Curing & Protection
  • Apply curing compound or use wet hessian cloth for at least 7 days.

  • Protect column pier from vibrations and impacts.

5.8 Finishing & Quality Inspection
  • Check concrete surface for honeycombs and cracks.

  • Conduct compressive strength tests on cube/cylinder samples.

  • Perform a final quality inspection before proceeding to the next phase.

6. SAFETY & ENVIRONMENTAL REQUIREMENTS

  • Workers must wear PPE (helmets, gloves, safety harness, and boots).

  • Follow proper lifting and hoisting procedures.

  • Maintain safety barriers around the work area.

  • Implement dust and noise control measures.

7. INSPECTION & TESTING

  • Pre-pour Inspection: Ensure formwork and reinforcement are in place.

  • During Pouring: Monitor slump, temperature, and vibration.

  • Post-pour Testing: Conduct compressive strength tests.

8. APPROVALS

This method statement shall be reviewed and approved by:

Prepared by:
Mark Arjay M. Arevalo
[Name]

Reviewed by:
QA/QC Engineer
[Name]

Approved by:
Project Manager
[Name]