METHOD STATEMENT FOR CONSTRUCTION OF COPING BEAM

METHOD STATEMENT FOR CONSTRUCTION OF COPING BEAM



1. SCOPE OF WORK

This method statement outlines the construction procedure for coping beam on a skyway project, including formwork installation, reinforcement fixing, concrete pouring, and curing.


2. REFERENCES

  • Approved Construction Drawings & Structural Plans

  • DPWH Standard Specifications

  • ACI 318 – Concrete Design and Construction Standards

  • ASTM A615 – Standard Specification for Reinforcing Steel

  • ACI 301 – Concrete Work Specifications


3. RESPONSIBILITIES

Project Engineer

  • Ensures compliance with construction drawings and specifications.

Site Supervisor

  • Manages workforce, materials, and equipment.

QA/QC Engineer

  • Ensures quality of materials and workmanship.

Safety Officer

  • Implements safety protocols and ensures worker compliance with PPE.


4. MATERIALS & EQUIPMENT

4.1 Materials

  • Ready-Mix Concrete (as per design mix)

  • Reinforcement Bars (Grade 40/60, as per approved bar bending schedule)

  • Formwork Materials (plywood, steel, or timber)

  • Curing Compound / Wet Hessian Cloth

4.2 Equipment

  • Concrete Mixer / Transit Mixer

  • Concrete Vibrator

  • Crane / Lifting Equipment

  • Scaffolding & Ladders

  • Surveying Tools (Total Station, Spirit Level, Theodolite)

  • Cutting & Bending Tools


5. METHODOLOGY

5.1 Pre-Construction Activities

  1. Survey & Layout

    • Verify coping beam dimensions and alignment using total station.

    • Mark reference points for reinforcement and formwork installation.

  2. Material Inspection

    • Check reinforcement bars for correct diameter, length, and bending.

    • Ensure formwork materials are free from defects.

    • Verify concrete mix design approval.


5.2 Formwork Installation

  1. Formwork Positioning

    • Install formwork firmly and securely along the edge of the skyway structure.

    • Use steel supports and bracing to prevent movement during concrete pouring.

  2. Alignment & Level Check

    • Use spirit level or laser level to maintain correct elevation and straightness.

    • Apply release agent for smooth stripping after curing.


5.3 Reinforcement Installation

  1. Placing of Rebars

    • Install reinforcement bars as per the bar bending schedule (BBS).

    • Ensure proper lap splicing and anchorage lengths as per design.

    • Maintain correct concrete cover using spacers and chairs.

  2. Tying & Securing

    • Use binding wire to secure rebars in position.

    • Inspect and approve reinforcement before proceeding with concreting.


5.4 Concrete Pouring

  1. Pre-Pour Checklist

    • Ensure formwork and reinforcement are properly secured.

    • Check slump test results (workability should match approved mix).

    • Ensure weather conditions are suitable for concreting.

  2. Concrete Placement

    • Use crane bucket / concrete pump to place concrete uniformly.

    • Pour concrete in layers to avoid segregation.

    • Use mechanical vibrators to remove air voids.

  3. Quality Control During Pouring

    • Perform slump test and compressive strength test (cube/cylinder samples).

    • Maintain proper curing temperature and avoid premature drying.


5.5 Formwork Removal & Curing

  1. Formwork Removal

    • Remove side formworks after 24–48 hours (or as per strength requirement).

    • Strip bottom supports after 7–14 days, depending on curing conditions.

  2. Curing Process

    • Apply curing compound or cover with wet hessian cloth for at least 7 days.

    • Keep surface moist to prevent cracking.

  3. Surface Finishing

    • Inspect concrete for honeycombs or voids.

    • Conduct repair work using Pressure Injection Epoxy (PIE) if necessary.


6. SAFETY REQUIREMENTS

  • Workers must wear PPE (helmets, gloves, safety boots, harness for heights).

  • Ensure proper scaffolding & edge protection during work.

  • Use tag lines & safety ropes when lifting materials.

  • Prohibit unauthorized access to the work area.


7. INSPECTION & TESTING

  • Pre-Pour Inspection – Ensure proper formwork and rebar placement.

  • Concrete Strength Test – Cube or cylinder tests at 7 & 28 days.

  • Final Inspection – Check dimensions, alignment, and surface finish.


8. APPROVALS

This method statement shall be reviewed and approved by:

Prepared by:
Project Engineer
[Name]

Reviewed by:
QA/QC Engineer
[Name]

Approved by:
Project Manager
[Name]