Monday, March 24, 2025

METHOD STATEMENT FOR INSTALLATION OF ANCHOR BOLTS, SOLE PLATE, AND GROUTING

 

1. SCOPE OF WORK

This method statement outlines the step-by-step procedure for the installation of anchor bolts and sole plates, including grouting between the coping beam and the sole plate, ensuring proper alignment, levelness, and structural integrity.


2. REFERENCES

  • Approved Construction Drawings & Specifications

  • DPWH Standard Specifications

  • ASTM C1107 – Standard Specification for Packaged Dry, Hydraulic-Cement Grout

  • ACI 351.1R – Grouting between Foundations and Bases


3. RESPONSIBILITIES

Project Engineer

  • Supervises execution and ensures compliance with the method statement.

Site Supervisor

  • Coordinates the installation crew and ensures materials are available.

QA/QC Engineer

  • Ensures correct anchor bolt placement, sole plate leveling, and grout application.

Safety Officer

  • Enforces proper PPE and safety procedures.


4. MATERIALS & EQUIPMENT

4.1 Materials

  • Anchor Bolts: As per approved drawing specifications.

  • Sole Plate: Prefabricated steel plates with required dimensions and machining.

  • Non-Shrink Grout: High-strength, non-shrink cementitious or epoxy grout (e.g., Sikagrout, Fosroc, BASF).

  • Shims & Leveling Plates: For temporary leveling of the sole plate before grouting.

  • Epoxy Adhesive: If specified for anchor bolts.

  • Cleaning Agents: Compressed air, acetone, or thinner for surface preparation.

4.2 Equipment

  • Drill Machine (if post-installed anchors are required)

  • Torque Wrench (for tightening bolts)

  • Leveling Instruments (spirit level, laser level)

  • Mixing Equipment (grout mixer, paddle drill, or manual mixing tools)

  • Concrete Vibrator (if deep grout application is needed)


5. METHODOLOGY

5.1 Pre-Installation Preparations

  1. Survey & Layout

    • Verify the exact locations of anchor bolts and sole plates as per construction drawings.

    • Mark the positions using chalk or markers.

  2. Material Inspection

    • Ensure anchor bolts, sole plates, and grout materials meet project specifications.

    • Check for defects, rust, or damages.

  3. Surface Preparation

    • Clean the coping beam surface where the sole plate will be installed.

    • Remove dust, oil, grease, or laitance.

    • Blow out dust from drilled holes (if post-installed anchor bolts are used).


5.2 Installation of Anchor Bolts

  1. For Pre-installed Anchor Bolts

    • Ensure bolts are correctly embedded in the coping beam during concrete placement.

    • Check verticality and alignment using a template before concrete sets.

  2. For Post-installed Anchor Bolts (If required)

    • Drill holes using the required depth and diameter.

    • Clean holes with compressed air.

    • Apply epoxy adhesive (if specified) before inserting anchor bolts.

    • Insert bolts and allow the adhesive to cure as per manufacturer’s instructions.

  3. Tightening of Anchor Bolts

    • Use a torque wrench to tighten the bolts to the specified torque value.

    • Verify alignment before proceeding to sole plate installation.


5.3 Installation of Sole Plate

  1. Positioning & Leveling

    • Place the sole plate over the installed anchor bolts.

    • Insert shims or leveling plates to achieve the required elevation.

    • Ensure proper alignment using a spirit level or laser level.

  2. Temporary Fixing

    • Spot weld or clamp the sole plate in position (if required).

    • Re-check alignment before proceeding with grouting.


5.4 Grouting Between Coping Beam and Sole Plate

  1. Grout Mixing

    • Prepare the non-shrink grout as per manufacturer’s specifications.

    • Maintain the correct water-to-powder ratio.

    • Mix thoroughly to achieve a uniform consistency (avoid excessive water to prevent strength loss).

  2. Formwork Preparation

    • Install a grout form around the sole plate to contain the grout.

    • Apply sealant to prevent leakage.

  3. Grout Application

    • Pour or pump the grout slowly from one side to avoid air entrapment.

    • Use a rod or vibrator to help the grout flow evenly under the plate.

    • Ensure full bearing contact between the sole plate and the coping beam.

  4. Curing of Grout

    • Cover the grout with wet hessian cloth or apply a curing compound.

    • Allow the grout to cure for 24 to 48 hours before removing formwork.


5.5 Final Inspection & Tightening

  1. Check for Voids & Defects

    • Inspect for shrinkage cracks or voids in the grout.

    • Conduct a hammer test to verify grout bonding.

  2. Final Torque Tightening

    • Tighten the anchor bolts to the final torque value as per specifications.

  3. Surface Finishing

    • Remove excess grout and clean the sole plate surface.

    • Apply protective coating (if required).


6. SAFETY REQUIREMENTS

  • Workers must wear PPE (helmets, gloves, safety goggles, safety boots).

  • Handle epoxy and grout with care, using gloves and masks.

  • Use proper lifting techniques when handling sole plates.

  • Ensure proper ventilation in confined areas during grout application.

  • Keep fire extinguishers nearby in case of welding-related tasks.


7. INSPECTION & TESTING

  • Anchor Bolt Alignment Check – Before and after tightening.

  • Levelness of Sole Plate – Using precision instruments.

  • Grout Strength Test – As per ASTM C109 (compressive strength test at 7 & 28 days).

  • Torque Test on Anchor Bolts – Ensure proper bolt tension.


8. APPROVALS

This method statement shall be reviewed and approved by:

Prepared by:
Mark Arjay M. Arevalo
[Name]

Reviewed by:
QA/QC Engineer
[Name]

Approved by:
Project Manager
[Name]

No comments:

Post a Comment

METHOD STATEMENT FOR CONSTRUCTION OF COPING BEAM

METHOD STATEMENT FOR CONSTRUCTION OF COPING BEAM 1. SCOPE OF WORK This method statement outlines the construction procedure for coping beam ...